How Much Spare Capacity Does Your VM Cluster Need?

Plan OpenShift Virtualization CPU and memory headroom for maintenance, host failures, and growth. Work through an example and adapt the capacity calculator.

How Much Spare Capacity Does Your VM Cluster Need?

Personal site note: views expressed here are my own and do not necessarily represent Red Hat or any other organization. The numbers below are an illustrative planning example. Use the support requirements for your release and validate the resulting design with representative workloads.

A six-host virtual machine cluster looks comfortable on an ordinary Tuesday. Then one host enters maintenance, another fails, and next quarter’s migration wave needs somewhere to run.

The capacity question is whether the remaining hosts can carry that load while the applications still meet their targets. A cluster-wide free-memory number answers only part of it.

For Red Hat OpenShift Virtualization, I would make the capacity review cover three things: resource requests that fit, application performance under the reduced capacity, and a valid destination for every affected VM. This post works through the arithmetic and includes a calculator you can adapt.

Define what must stay running

Write the operating requirement as a scenario before choosing a spare-capacity percentage:

  • All hosts are available during the normal application peak.
  • One host is unavailable for planned maintenance.
  • One host fails while that maintenance is still in progress.
  • The same conditions occur after the next migration wave or growth period.

Decide which scenarios the service must tolerate and what interruption is allowed. Maintenance plus a separate host failure requires two hosts’ worth of capacity to be unavailable at once. If policy instead pauses maintenance after a failure, record that limitation and how the team enforces it.

Count only hosts eligible to run these workloads. Dedicated control-plane machines, a different CPU pool, or a worker with no access to the required storage cannot be silently added to the recovery budget. Model a rack or zone failure separately if that is the promised failure boundary.

An N+1 statement also needs a recovery procedure. Spare resources alone do not establish that a failed host’s VMs restart safely or within the required time. The host-failure guide covers the fencing and recovery side of that design.

Keep requests, consumption, and guest sizing separate

A VM’s configured vCPUs and guest RAM describe what the guest sees. The resources requested by its launcher pod describe its scheduling footprint. Measured consumption describes what it used during an observed workload. Keep all three in the inventory.

The Kubernetes scheduler uses resource requests when choosing a node. Low current utilization does not make a pod schedulable when its requests do not fit. See the Kubernetes resource-management documentation. At the same time, a request that fits does not prove the application will meet its latency or throughput target when other guests become busy.

For each resource, compare the total effective VM pod requests with the concurrent demand measured under representative load. Use the larger as the aggregate planning load in the simple model below. Include VM overhead in both sides of that comparison. This conservative screen still needs per-node placement checks and application testing.

Measure the workload together. Adding every VM’s individual historical peak can overstate concurrency; averaging an entire month can hide the batch window that matters. Retain the observation interval, application activity, and any missing guest telemetry. The benchmark guide provides a way to build that evidence before a migration wave.

For CPU, use a consistent unit across budgets and demand. Kubernetes CPU units are the units used here; 1000m is one CPU unit. Do not divide a vCPU inventory by a physical-core count and treat the resulting ratio as a measured performance limit. CPU generation, simultaneous multithreading, dedicated CPU placement, and application behavior affect the result.

Establish the budget available to VMs

Start from each worker’s reported allocatable CPU and memory. Account for the non-VM workloads that must run there, including virtualization services, monitoring, networking, and any colocated storage. Leave the operating margin that your performance tests require.

System reservations already reflected in allocatable should not be subtracted a second time. Conversely, allocatable has not subtracted the requests of pods already running on the node. Reconcile the numbers rather than mixing installed RAM, allocatable memory, and a dashboard’s free memory.

Red Hat documents additional platform and per-VM overhead in the OpenShift Virtualization installation requirements. Use those requirements to estimate a new environment, then inspect the actual VM pod footprint and platform load. If you already counted the launcher pod’s effective request, do not add that same VM overhead again.

The calculator calls the result the per-worker VM budget. It is the amount this plan allows VMs to consume on each surviving worker, after the other commitments and operating margin have been accounted for.

For a compact cluster or workers that also provide storage, those other commitments can change during a failure or rebuild. Use the budget for the scenario being tested. A steady-state deduction can be too small for that case.

Work through a six-worker example

Assume six identical VM workers with compatible CPUs and shared storage. The control plane runs elsewhere. Every VM in this example can use every worker, and all can follow the planned maintenance procedure.

These are illustrative inputs, with VM overhead already included in the workload figures:

InputCPUMemory
VM budget per worker56 CPU units448 GiB
Current aggregate VM planning load190 CPU units1,400 GiB
Growth through the planning horizon20%20%
Additional temporary load during operations8 CPU units64 GiB

The temporary allowance represents additional work that must coexist on the surviving workers, such as migration or import activity. It is an assumption to validate, not an OpenShift default. Count only extra demand that is absent from the workload total and the per-worker deductions.

Apply growth to the workload, then add the temporary allowance:

1
2
Planned CPU    = 190 × 1.20 + 8  = 236 CPU units
Planned memory = 1,400 × 1.20 + 64 = 1,744 GiB

Now remove the unavailable workers from the supply side:

ScenarioAvailable VM budgetRemaining CPURemaining memory
All six workers available336 CPU units / 2,688 GiB100 CPU units944 GiB
One worker unavailable280 CPU units / 2,240 GiB44 CPU units496 GiB
Maintenance plus a separate failure224 CPU units / 1,792 GiB−12 CPU units48 GiB

The six-worker plan covers the aggregate load with one worker unavailable. It has a CPU shortfall when two are unavailable. Memory still fits on paper, but that does not cancel the CPU deficit.

For this uniform pool, the arithmetic is:

1
2
3
4
5
Survivors needed = round up the larger of:
                  planned CPU / per-worker CPU budget
                  planned memory / per-worker memory budget

Total workers = survivors needed + simultaneously unavailable workers

Here, CPU needs five survivors, while memory needs four. Add the two unavailable workers and the arithmetic floor is seven workers. That floor assumes the workloads can be packed onto those survivors. It still needs placement and performance validation.

Another option is to reduce or defer demand, or agree to a narrower maintenance and failure scenario. Make that decision explicitly before the next wave consumes the remaining capacity.

Try the capacity calculator

The calculator uses the example above. It assumes one pool of identical workers and applies the same growth percentage to CPU and memory. Run separate cases for different pools or workload mixes. A negative remainder is a shortfall; a positive remainder is capacity left within the budgets you entered.

CPU and memory scenario
Use net VM budgets and a consistent CPU unit. The example values are editable.

For a more detailed forecast, replace percentage growth with the actual next-wave inventory and revised VM sizes. You can enter those future totals as the current load and set growth to zero. Keep temporary operational demand separate.

Check whether each VM has somewhere to land

Aggregate capacity is a useful first screen. It cannot prove placement.

Suppose four eligible destinations each have 96 GiB remaining within their VM budget. Together they have 384 GiB free. A VM whose complete scheduling footprint is 128 GiB still cannot fit on any of them without first moving or removing another workload.

Repeat that check with the actual constraints: CPU compatibility, node selectors, required affinity and anti-affinity, taints, storage access, huge pages, device availability, and topology. A 128 GiB VM that can use only two workers has a two-worker capacity problem, even if the cluster contains twenty workers.

Inspect the largest guests and the most restricted pools first. For a mixed-size cluster, remove the specific failed or maintained nodes from the model. Subtracting an average host can hide the loss of the largest worker or the only compatible destination.

Reserve enough capacity to complete maintenance

Red Hat’s live-migration requirements include shared RWX storage, compatible CPUs, and enough memory and network capacity. Its approximate spare-memory calculation multiplies the maximum number of concurrently draining nodes by the highest total VM memory requests on a node. Use that check alongside the survivor calculation and the per-VM placement review.

The same guidance strongly recommends a dedicated Multus network for live migration to reduce the impact of network saturation on tenant workloads. Include that network in the design and test its bandwidth under the planned drain concurrency. A dedicated network still needs sufficient capacity for the migrations using it.

A live migration needs resources at the destination while the source VM is still present. A cluster-wide memory sum can conceal that overlap. The example removes draining workers’ budgets entirely, so do not add all their guest RAM again as a blanket migration allowance. Account for additional activity on the surviving workers and test the actual sequence.

Available capacity also needs to last for the maintenance window. Large guests with rapidly changing memory can take longer to migrate; concurrent moves compete for bandwidth. Rehearse the intended drain concurrency with representative application load and record completion times. The upgrade guide connects that rehearsal to node drains and guest evacuation.

For guests that cannot live migrate, include the agreed shutdown and restart path in the plan. A restart does not remove the need for an eligible destination when the original host remains unavailable.

Treat overcommit and storage as separate decisions

Reducing a memory request can make the scheduling arithmetic fit while leaving the real workload demand unchanged. Red Hat’s higher VM density guidance describes memory overcommitment and warns of performance effects under high utilization. Validate any overcommit policy during the reduced-host scenario, including guest pressure, host pressure, and application latency.

Likewise, a CPU allocation ratio does not guarantee a particular amount of application throughput. Test shared-CPU workloads together. Review dedicated CPUs, NUMA placement, and devices in their own eligible pools.

This calculator covers CPU and memory. Storage still needs its own capacity and performance review: destination disks, snapshots, migration scratch space, backup retention, growth, and rebuild activity. Network bandwidth must cover application, storage, backup, and migration traffic that share the same links. The storage performance guide is the companion review for those limits.

Turn the estimate into an admission decision

Before accepting the next wave, retain the inventory and workload evidence, the scenario being protected, the remaining per-node budgets, and the results of a maintenance rehearsal. Exercise host failure in an isolated, representative environment with an agreed recovery procedure.

Put the resulting evidence and unresolved constraints in the production readiness scorecard. Repeat the calculation when a wave lands, a VM grows, a placement rule changes, or maintenance concurrency increases. Keep the forecast horizon long enough to cover the time needed to acquire and prepare more capacity.

The solutions architect takeaway

  1. Name the scenario. One host unavailable and one host failing during maintenance are different capacity commitments.
  2. Budget what VMs can actually use. Account for platform work, VM overhead, and the operating margin once.
  3. Check CPU and memory independently. In the example, CPU requires an additional worker even though aggregate memory still fits.
  4. Prove placement and performance. Every affected VM needs an eligible destination, and the application still has to meet its target.
  5. Revisit the plan before admitting growth. Use the next wave and the hardware lead time to set the review date.